Masthead Placeholder
 
Project History

 

  • Implementation Approach
    • Design and build project team is Cianbro Corporation, and Vanderweil Engineers
  • Explored alternative financing methods for the $8.5 million project and considered:
    • Internally financed project
    • Third party built, own and operate
    • Third party capital lease
  • Applied in 2004 for funding under a solicitation offered by Oak Ridge National Laboratory on behalf of the U.S. Department of Energy for demonstration of integrated distributed energy systems.  Under that competitive solicitation, EMMC was successful in obtaining a $3,000,000 award. The balance will be internally financed.

Why EMMC is a good applicant for Combined Heat and Power 
  • High Utility Rates
  • High Process Thermal Load
  • Twelve month thermal requirement for heating or cooling
  • Match between electric and thermal loads
  • 24-hour, seven day a week operation
  • High pressure natural gas availability
  • Operations and departments with critical load requirements
  • Attractive return on investment and annual operating cost savings
  • Significant annual savings
  • $3 million award from the United States Department of Energy

Project Approval Process  
  • Internal: approval by the EMMC Board of TrusteesExternal: approval through a mandatory state Certificate of Need ProcessAir Permit ApplicationCity and local permitsSystem Configurations
    • Solar Centaur 50, 4.4 Mwe @ ISO with un-fired HRSG generating 25,000 PPH steam
    • New 500 ton steam absorption chiller and ancillaries
    CHP projected key financial figures
    • $5.5 million project net capital cost
    • $1.1 – $1.2 million annual operating
    Benefits of Combined Heat and Power
    • Energy savingsPower qualityReliabilityIndependence
    • Reduced air emissions
    Reliability
    • Reduced impact of potential electrical grid power loss (local or regional)Backed up by the existing emergency diesel generatorsBacked up by the utility grid during maintenance shutdowns and unplanned outage periods
    • Backed up by the existing steam boiler plant
  • Reduced Emissions
    • Reduce emissions for NOx, CO, SO2, VOCs, PM, and other Green House Gases as compared to the existing combination of the Electric Power Plants and EMMC’s steam plant